4.03 Runbooks, Operational Documentation and Readiness Review

Phase 4: Finalization · Previous: 4.02 Security Assessment · Next: 4.04 Release Candidate, Cutover Plan and Open-Source Release


1. Overall Objective Make sure the system can be operated at 3 a.m. by following documents alone.

2. The Problem We Are Solving The knowledge lives in one person’s head, which is a single point of failure.

3. Concepts and Research

  • Runbook structure (symptom → diagnosis → action → verification).
  • Incident severity levels.
  • Post-incident review practice.

4. Implementation Tasks Complete runbooks for:

  • every alert
  • period close
  • reconciliation breaks
  • offline conflicts and disputes
  • key rotation
  • restore
  • deploy and rollback
  • partition maintenance
  • emergency freeze (stop all postings safely)

Also:

  • Write the incident response plan.
  • Go through the production readiness checklist (README) item by item, attaching evidence.

5. Testing Requirements A tabletop exercise: walk through 3 incidents using only the runbooks, and fix the gaps found.

6. Deliverables Runbooks, incident plan and the completed checklist with evidence links.

7. Acceptance Criteria Every checklist item is either evidenced or explicitly marked “not met” with a plan.

8. Dependencies Steps 3.09–4.02.

9. Estimated Difficulty Medium.

10. Exit Gate Readiness review held and recorded.