1. Overall Objective Produce v1.0.0-rc, the first client’s cutover plan, and the public open-source release.
2. The Problem We Are Solving Going live must be a reversible, criteria-driven decision, not a deadline.
3. Concepts and Research
- Go/no-go criteria.
- Cutover patterns: flip the authoritative ledger behind a flag, with the old ledger becoming the shadow for a period so rollback is possible.
- Semantic versioning.
- Open-source governance (contributing guide, code of conduct, licence).
4. Implementation Tasks
- Cutover plan:
- Freeze window.
- Final replay check.
- Flip the flag.
- Old ledger becomes the shadow.
- Rollback trigger conditions and procedure.
- Write the go/no-go criteria.
- Tag v1.0.0-rc.1.
- Public repo hygiene: README, LICENSE, CONTRIBUTING, SECURITY, architecture docs, examples.
5. Testing Requirements
- Rehearse the cutover and the rollback twice in staging.
6. Deliverables Release candidate, cutover plan and the public release.
7. Acceptance Criteria Cutover and rollback rehearsed successfully, and the go/no-go criteria agreed.
8. Dependencies All weeks.
9. Estimated Difficulty Medium.
10. Exit Gate The cutover happens only when the go/no-go criteria are met, which may be after step 4.04. Shadow mode should have run at least 30 clean days before the flip.